[GEM] Milestone 1: MVP Launch

Start Date: 2026-02-03 Target Date: 2026-03-14

Gantt Chart

Task / Deliverable Owner Status Start End
PHASE: DISCOVERY
Environment provisioned by Customer + Documentation Handoff GTM Complete Dec 17 Dec 17
Documentation Handoff (user stories, meetings, discussions, etc) GTM Complete Dec 17 Dec 17
Technical Architecture and Data Discovery Review TSA + DATA + CE Complete Dec 17 Dec 18
SOW Build All Teams Complete Dec 18 Dec 19
SOW Signed and Approved GTM + Customer Complete Dec 19 Dec 20
Linear Project Setup CE + TSA + DATA Complete Dec 19 Dec 20
Internal Project Kickoff (Gantt Chart Approved) All Teams Complete Dec 20 Dec 20
◆ GATE 1: Discovery Complete Dec 17 Dec 20
PHASE 1: FOUNDATION
Set up COE tenant access TSA Not Started Feb 03 Feb 04
Set up AWS infrastructure CE Not Started Feb 03 Feb 05
Create users and roles CE Not Started Feb 04 Feb 05
Connect Google Calendar CE Not Started Feb 05 Feb 06
Set up video calls integration CE Not Started Feb 05 Feb 06
Set up staging and dev environments TSA Not Started Feb 04 Feb 06
Backdating API dependency on GEM side TSA Not Started Feb 03 Feb 07
◆ GATE 2: Foundation Complete Feb 03 Feb 07
PHASE 2: SEED DATA
Create jobs and pipeline stages CE Not Started Feb 07 Feb 10
Add offices and locations CE Not Started Feb 07 Feb 08
Add departments and teams CE Not Started Feb 07 Feb 08
Create scorecard templates TSA Not Started Feb 10 Feb 11
Design candidate data schema DATA Not Started Feb 07 Feb 11
◆ GATE 3: Seed Data Complete Feb 07 Feb 11
PHASE 3: DATA GEN
Define how to spread applications DATA Not Started Feb 11 Feb 12
Generate fake candidates and applications CE Not Started Feb 12 Feb 14
Create historical pipeline movements CE Not Started Feb 14 Feb 17
Plan interview schedule distribution DATA Not Started Feb 12 Feb 13
Generate resumes for candidates CE Not Started Feb 14 Feb 15
Add notes and emails to candidates DATA Not Started Feb 15 Feb 17
◆ GATE 4: Data Gen Complete Feb 11 Feb 17
PHASE 4: INGESTION
Create scheduled interviews CE Not Started Feb 17 Feb 19
Design scorecard responses DATA Not Started Feb 17 Feb 18
Add scorecards to interviews CE Not Started Feb 19 Feb 20
Set up Story 1 - AI Application Review TSA Not Started Feb 18 Feb 20
◆ GATE 5: Ingestion Complete Feb 17 Feb 20
PHASE 5: STORIES
Set up Story 2 - Interview Scheduling TSA Not Started Feb 20 Feb 21
Set up Story 3 - Team Collaboration TSA Not Started Feb 21 Feb 24
Set up Story 4 - Executive Dashboards TSA Not Started Feb 24 Feb 25
Set up Story 5 - Source ROI TSA Not Started Feb 25 Feb 26
Set up Story 6 - Talent Rediscovery TSA Not Started Feb 26 Feb 27
Run internal QA on all stories TSA Not Started Feb 27 Mar 03
Demo to internal stakeholders TSA Not Started Mar 03 Mar 03
◆ GATE 6: Stories Complete Feb 20 Mar 03
PHASE 6: VALIDATE
Fix bugs from QA CE Not Started Mar 03 Mar 05
Run UAT with customer GTM Not Started Mar 05 Mar 07
Final fixes after UAT CE Not Started Mar 07 Mar 09
◆ GATE 7: Validate Complete Mar 03 Mar 09
PHASE 7: LAUNCH
Deploy to production CE Not Started Mar 10 Mar 10
Walk customer through the demo GTM Not Started Mar 10 Mar 11
Write documentation package TSA Not Started Mar 10 Mar 12
Hypercare support period GTM Not Started Mar 10 Mar 14
Close out the project GTM Not Started Mar 14 Mar 14
✓ MILESTONE 1 COMPLETE: MVP LAUNCH Feb 03 Mar 14

Summary by Role

Role Tasks Days
TSA (Thiago) 14 ~20
CE (Taufer) 15 ~25
DATA (Thais) 6 ~10
GTM (Shivani) 5 ~10

Timeline Visual

Week    Feb 03  Feb 10  Feb 17  Feb 24  Mar 03  Mar 10  Mar 14
        W1      W2      W3      W4      W5      W6
        ├───────┼───────┼───────┼───────┼───────┼───────┤
FOUND   ████████
SEED            ████████
DATA                    ████████
INGEST                          ████
STORIES                         ████████████████
VALID                                           ████████
LAUNCH                                                  ████████

Draft v1 - 2026-02-03