WBS Tool - CLAUDE.en.md

English translation of CLAUDE.md (the Japanese original is the primary spec). Sync rule: whenever the spec changes, update CLAUDE.md and CLAUDE.en.md in the same commit.

A text (JSON) driven WBS / Gantt + inazuma-line tool. wbs.json (data) is the single source of truth; the self-contained single HTML wbs_viewer.html renders it.


Product vision & design principles (#67)

A local WBS for the AI-era manager (PL / tech lead) leading a small, elite team that includes AI. Humans edit via the GUI; AI edits via raw JSON and CLAUDE.md — the same plan.

  • Target user: not the enterprise PM of huge projects, but a manager (PL / tech lead) leading a ~10-person elite team that includes AI. The author is this persona (dogfooding).
  • Vision (a bet, owned as such): as AI rises, small elite teams wielding AI become the norm, and everyone becomes a PL/TL. This tool is for that lead (human and PL/TL agent) to manage the plan. It is a bet on the future, but hedged — even if it misses, it already helps today's leads.
  • Core differentiator = two first-class interfaces: human = GUI / AI = raw JSON + the AI-readable CLAUDE.md. Both are first-class. Every feature works via both the GUI path and the AI/JSON path (custom keys preserved, round-trip).
  • CLAUDE.md is not "documentation" but "the AI's API spec": because AI depends on the format, the schema is kept almost frozen.
  • Build: AI-native (progress assessment, dependency inference) / honest views (true state, not vanity) / load by assignee (human vs AI) / cost (_ai tokens, _money).
  • Don't build: enterprise PM (portfolios, complex permissions) / large-scale real-time collaboration / heavy workflow engines / approval flows.
  • Background essay (Japanese) → WBSという至高ツールで、このAI時代をサバイブする

Handling principles (important)

  • Do not touch wbs_viewer.html (the viewer) as a rule. The view logic is complete.
  • Changes mean editing wbs.json (data) only. When asking an AI to do work, it should edit the JSON.
    • Touch the HTML only when the display spec itself must change (and only on explicit request).

Archiving (pruning past tasks)

To keep the file from growing forever, move old completed tasks out of the current file:

  • Trigger: when completed tasks from past months (e.g., May 2026 and earlier) have scrolled into the past on the Gantt.
  • Steps:
    1. Create a backup in the same folder (e.g., collect the moved tasks into wbs-archive-2026-05.json).
    2. Delete those completed tasks from wbs.json.
  • → The current wbs.json stays focused on "now and the future"; history is preserved in archive JSONs.
  • Scale is managed in two layers: collapsing (display) + this archiving (data).

Requirements

  • Google Chrome (latest) recommended. Chromium-based browsers (e.g., Edge) work too (testing is done on Chrome). Firefox/Safari are not supported (no File System Access API).
  • On corporate-managed browsers, editing is unavailable if File System Access is disabled by policy (viewing still works).
  • No HTTP server, no external libraries / CDN. Open wbs_viewer.html directly via file://.

Opening / reloading

  1. Open wbs_viewer.html in Chrome.
  2. Pick wbs.json via Open file (or drag & drop onto that same button).
  3. Edit wbs.json and save → press Reload to re-read and re-render (no re-selection needed / File System Access API).
  4. Collapsing: click a ◆project / L1 / L2 ▼/▶–name. The ▼/▶ in the Task column header expands/collapses everything (▼ = all open → click collapses all; ▶ = something closed → click expands all). An accidental header action can be restored with Ctrl+Z (inactive while an input has focus).
  5. Scroll position is preserved across collapsing and reloads; only loading a new file re-centers on today and resets collapse state.

In-browser editing (edit mode)

In addition to text / AI editing, wbs.json can be edited directly on screen (optional feature).

  • The Edit button toggles ON/OFF (green = ON). When ON, the left table becomes inputs + action buttons.
  • Supported: inline editing of every field (No.=id / task name / qty / hours / assignee / plan & actual dates / notes), progress input (the leaf's ◀ N% ▶ stepper changes _progress by ±10%; setting ≥10% auto-sets actual.start to today / returning to 0% keeps the start date), adding leaves (row = sibling below; project row +Task; ids are minted collision-free; adding to a collapsed project auto-expands it), nesting (add a child task) (row +子/+sub: on a leaf it becomes a summary node carrying its values into child 1 = effort/progress unchanged; on a summary it appends a blank child; child id = parent id + suffix; not shown on the 3rd level = no 4th level), deletion (, with confirmation, including children; deleting the last child of a summary returns that child's values to the parent and demotes it to a leaf = effort is never lost), reordering among siblings (▲▼), milestone editing (+MS on the project row / an edit row below it with date (📅) · name · color · ✕ delete. Color is chosen from 5 CUD-safe Okabe-Ito presets — the GUI uses a picker, not free hex; JSON/AI can still set any #hex), reschedule (#96) (the leaf row's = record the plan change into _planLog and auto-update the plan; see _planLog in the Data section).
  • Autosave: changes are written back to wbs.json after a ~0.4 s debounce (File System Access API). Writes are serialized through a single queue. Only the internal derived values _calc/_leaf are stripped (user keys starting with _ are preserved). Save status (Unsaved changes… / Saved HH:MM:SS / Save failed) is always visible at the top right.
  • External-change detection: before each write the file's mtime is checked; if it changed outside the tool (e.g., AI editing), an overwrite confirmation is shown. When asking an AI to edit, it is safest to turn edit mode OFF first.
  • Auto-retry on interference: when a sync client (OneDrive, etc.) or antivirus touches the file at the same instant as a save, the browser may reject the write with InvalidStateError ("state had changed since it was read from disk"). In that case the tool waits a beat and retries the save once (the retry's getFile() refreshes the browser's internal snapshot, which almost always recovers). The write is rejected before touching disk, so the original file stays intact. If the retry also fails, it shows "Save failed" and keeps the dirty flag (re-saved on the next edit or on tab close; it does not auto-retry in a loop, to avoid alert spam).
  • Prerequisites: saving requires write permission. Only files opened with a handle (Open file or D&D) are editable. file:// pages cannot show write-permission prompts, so when turning Edit ON you re-select the same wbs.json in a save dialog (the selection itself grants permission). ⚠ Chrome truncates the file the moment it is picked, so the current data is written immediately after selection (never left empty — #29). If told to "press Edit again", do so (browser gesture limitation; the second click opens the dialog directly). The permission is session-scoped (after restarting Chrome, re-select once per Edit ON). Loading a new file automatically turns edit mode OFF (turn it ON again to grant permission for the new file). On a failed load the handle is not replaced (prevents overwriting the wrong file).
  • Legacy format ({project,tasks}): on Edit ON, after confirmation it is converted to the projects[] format before editing.
  • Date cells are YYYY-MM-DD text inputs plus a 📅 calendar button. 2026/07/01-style input is accepted and normalized to -. (The display format of input type=date follows the browser UI language and cannot be controlled, so the display is fixed to ISO — #33.)
  • Input guards: dates are valid only within 1900–2099 (out-of-range / partial input is ignored, not saved). Qty / hours accept decimals (step="any"). Mouse-wheel changes on number inputs are disabled (prevents accidental edits). Closing the tab with unsaved changes prompts for confirmation.
  • Out of scope (by design): drag-and-drop reordering / moving across parents / automatic renumbering / adding projects. Use JSON or AI editing for those. (leaf↔summary conversion is now handled in the GUI via +子/deleting the last child = #70)
  • Effort / progress / inazuma line recompute automatically as before (re-rendering is deferred while an input has focus).

Data (wbs.json)

  • Multi-project. Top level is projects: [{ name, milestones, tasks }].
    • The legacy format (single { project, milestones, tasks }) is still readable (backward compatible).
  • Holidays (optional, top-level): holidays: ["YYYY-MM-DD", { date, name }] (string form = no name / object form = name as tooltip). Shared across all projects. Holiday dates render red in the date header, and weekend + holiday columns are shaded faint pink full-height in the Gantt. If omitted, only weekends are pink (backward compatible). e.g. "holidays": [{ "date": "2026-07-20", "name": "Marine Day" }] (2026 Japanese holidays ship in wbs_roadmap.json/wbs_sample.json).
  • Each project's tasks nest parent-child (max 3 levels). With children = summary node; without = leaf (carries effort).
  • Leaf fields:
    id, name, qty, hours (per unit), assignee,
    plan:   { start, end }        planned, "YYYY-MM-DD"
    actual: { start, end }        actual (null if undecided)
    note
    _anyName                      "_"-prefixed = custom key (optional, ignored by viewer, preserved on save)
    
  • Effort and progress are not stored in the data (all derived; computed by the JS in the HTML).
  • Keys starting with _ may be added freely (ignored by the viewer by default, preserved by edit-mode saves). Use them for metadata (e.g., _ai in wbs_roadmap.json = recorded AI effort in tokens; entirely optional. wbs_sample.json is the minimal example without custom keys).
  • Exception: _progress (0/10/…/100) is read by the viewer as the progress value (EV), alongside _progressAt (assessment time, ISO) and _progressBy ("manual" or a model name). Asking an AI: "assess task X's progress to the nearest 10% from the deliverable and requirements" → it writes _progress/_progressAt/_progressBy on the leaf. If unset, progress falls back to time-based (backward compatible).
  • _planLog (schedule-change history, #96): a _ key that records as fact why a successor was pushed back by a delay (same idea as _progress/_ai — not derived; the viewer preserves it by default). Append one entry per reschedule (append-only). The first entry's from is effectively the baseline (the original plan):
    "_planLog": [
      { "at": "2026-06-10T09:00:00Z",
        "from": { "start": "2026-06-01", "end": "2026-06-05" },
        "to":   { "start": "2026-06-15", "end": "2026-06-19" },
        "by": "manual", "reason": "pushed back by the delay in #504" }
    ]
    • at = change timestamp (ISO) / from·to = plan before·after / by = "manual" or a model name / reason = why (e.g. the upstream #N).
    • AI-native: "push B back by a week and record the reason = delay in #504" → the AI updates plan and appends one line to _planLog.
    • GUI path (edit mode): the leaf row's ↷ button → form (new start / new end / optional reason) → "Confirm" = appending to _planLog + auto-updating plan + autosave, all in one click (structurally prevents half-done updates). Editing a date cell directly is a "correction" = not recorded (intent is separated from rescheduling). No-change confirms are not recorded. There is no GUI deletion of history (fix via JSON if needed).
    • Display: only the latest change gets a trail (dotted gray; bottom lane = start moved, top lane = end moved — the lane tells the change type). The task name gets ↷N (count of valid entries). Click ↷N or a rescheduled plan bar to open a balloon = full history (when, from → to, ±N days, reason) plus vs-baseline. Click outside / Esc closes. No extra rows; gantt ink stays constant no matter how many reschedules. Trail origins are automatically included in the time-axis range. Broken entries are ignored (graceful; tests/異常_リスケ履歴.json).
    • Scope: recording is limited to changes of plan (no full-field audit log).
  • milestones: [{ date, label, color }] is optional per project.

Adding / updating data (how-to)

Edit wbs.json only. Save → press Reload in the viewer.

① Status updates (daily operation — most important)

Progress, effort, and the inazuma line are computed automatically. You only touch the actual dates:

  • Work started → set actual.start on the leaf (→ the Actual-End column shows "active"; reflected in the inazuma line)
  • Work finished → set actual.end (→ row turns gray with ; the inazuma point sits on the today line)
  • Plan changed → fix plan.start / plan.end

② Adding a task

Append a leaf to a summary node's children. Keep name a concise label (guideline: ~14 full-width chars; put details and context in note) — long names don't break anything but get truncated in the task column (full text on hover).

{ "id": "2.1.3", "name": "New task", "qty": 1, "hours": 16, "assignee": "piguo",
  "plan":   { "start": "2026-07-01", "end": "2026-07-05" },
  "actual": { "start": null, "end": null }, "note": "" }
  • To add an intermediate phase, add a summary node with children and put leaves under it (max 3 levels).

③ Adding a project

Append to the projects array:

{ "name": "New project", "milestones": [],
  "tasks": [ { "id": "1", "name": "Phase 1", "children": [ /* leaves… */ ] } ] }

④ Adding a milestone

Append to the project's milestones:

{ "date": "2026-09-30", "label": "Release", "color": "#ef4444" }

⑤ Example requests to an AI (have it edit the JSON)

  • "Mark the design review as completed today" → set actual.end of that leaf to today
  • "Component placement has started" → set actual.start
  • "Add a testing phase" → append a summary node + leaves
  • "Archive everything completed before May" → archiving procedure above (backup + delete)
  • "Assess the progress of task X" → see "AI progress assessment" below (deliverable + requirements → nearest 10% into _progress)

⑥ AI progress-assessment workflow (this tool's core = AI-native)

Hand the fuzzy "roughly what %" to an AI. The steps are deterministic:

  1. Read the leaf's requirements (issue URL / acceptance criteria in note, related commits/deliverables).
  2. Compare deliverable vs. requirements and estimate completion, quantized to the nearest 10% (0/10/…/100) (don't over-credit; don't count unverified work).
  3. Write three keys on the leaf: _progress (the value) / _progressAt (assessment time, ISO) / _progressBy (the assessing model's name, or "manual" for a human).
  4. Done is separate: when actually finished, set actual.end (= 100%) rather than _progress. _progress is only an in-progress earned-value estimate.
  • Example: "Assess #63's progress from the deliverable (impl/tests/docs) and acceptance criteria, to the nearest 10%."
  • Note: an assessment is a recorded fact (a person/AI judgment at that moment); it is not recomputed, hence a _-key — consistent with "no derived values in data."

Computation (deterministic, in the HTML)

  • Effort (person-days) = qty × hours ÷ 8. Parent = sum of descendant leaves.
  • Parent plan/actual period = min start – max end of descendant leaves.
  • Progress (EV = earned value / reference date = today):
    • Not started (no actual.start) = 0% / Completed (actual.end set) = 100%
    • Active = if _progress (0/10/…/100) is present, quantize to the nearest 10% and use it; otherwise fall back to the time-based clamp((today − actual.start) ÷ (plan.end − plan.start) × 100, 0, 100) (backward compatible).
    • Parent = effort-weighted average of descendant leaves' (progress × effort) (continuous; not snapped).
  • EVM values: EV = actual progress / PV = planned = what should be done by today clamp((today−plan.start)/(plan.end−plan.start)×100,0,100) (linear; parents weighted) / slip = behind = max(PV−EV,0) (≈ EVM SV). S-curve, non-linear PV, and a cost axis are out of scope (not done).
  • Header summary (right, #71): Period (earliest start–latest end / business days left, excl. weekends & holidays (holidays) #75) / Effort (person-months = person-days ÷ 20 working days / remaining) / Progress (actual EV% / planned PV% / behind = max(PV−EV,0)%), in three rows plus a meta line (📄 filename · N projects · 📅 today · 🔄 refreshed · 💾 saved). Each row has a hover tooltip.
  • Delay badges (4th summary line "Behind:"): the overall behind% is textbook EVM (ahead-work offsets it, so it can read 0%); to avoid missing slippage, the count of tasks behind is shown as badges (Due = past planned end & not done / EV = PV>EV). A badge whose count is 0 is hidden; if both are 0 the whole line is hidden.
  • Progress column = ◀ N% ▶ stepper (10% steps; editable on leaves only / parents show the auto-aggregate read-only, continuous). _progress is not a derived value but "a person's/AI's judgment at a point in time", so it is stored as a _ key (never recomputed) — consistent with the "no derived values in data" rule.
  • Status column = behind / actual / planned (slip / EV / PV, %). Behind=red, actual=blue, planned=black. On-track rows show actual only (quiet). No mental math (the delay is pre-computed).
  • Planned-end turns red when today > plan end and not done (deadline overrun; done rows are not reddened). Same "red = behind" as the time tab's Gantt/inazuma.
  • The right pane toggles between "Time / Progress" tabs (default = Time). Time = the Gantt (unchanged) / Progress = horizontal completion bars (blue=actual / red=shortfall to plan, whose right edge = planned PV / thick=leaf, thin=parent summary, same sizes as the time view). Only the active view is injected into the DOM (render cost = one view). The tab choice is remembered in localStorage.
  • Telling the Progress view apart from Time: (1) square-cornered bars (Time = rounded; distinguished by shape, CUD-safe) (2) a blue-grey unfilled track (#eef1f7, 0–100%) (3) ruler-style ticks = major (full-height dotted at 20/40/60/80%, #555) + minor (short solid from the top edge down ~60%, every 10%, same #555, drawn in front of the bars). Axis labels are 0/20/40/60/80/100%.

Display

  • UI is Japanese/English switchable (the "EN / 日本語" toolbar button). Default Japanese; the choice is stored in localStorage.
  • Plain-branding toggle (#79): clicking the title (logo / "WBS Viewer") at the top-left hides the logo, version, "Viewer" and the tab title, leaving just "WBS" (click again to restore; remembered in localStorage). It strips the product look so the tool can pass as "self-made" on locked-down client sites. No tooltip is added (to keep it undiscoverable). All UI strings live in the I18N table inside the HTML (data = the contents of wbs.json is never translated). When adding a UI string, add it to both ja and en.
  • State filter (#91): three pill toggles in the "filter bar" (a full-width band just above the left info table) ("State: To do / In progress / Done") show/hide rows by state (default all-ON; remembered in localStorage wbsStateFilter; i18n ja/en). It lets you focus on unfinished work when completed tasks pile up. Display-only — it merely thins the rows; neither wbs.json (data) nor the horizontal axis (time range) changes: the axis is fixed from the full data, so the remaining bars don't move a single pixel (hiding is a blindfold, not a delete). State is the exclusive 3-way split of the existing progress logic (To do = no actual.start / In progress = start set, no end / Done = actual.end set), evaluated via a STATES table. Parent-retention: a parent stays if at least one descendant remains visible; otherwise the parent (and project) is hidden too. The top-right summary (effort/progress/delay) stays unchanged, counting completed work (honest view). A hidden pill shows a strike-through so it reads without relying on color (CUD redundancy).
  • Delay filter (#92): a "Delayed only" toggle in the same filter bar (default OFF; remembered in localStorage wbsDelayOnly). When ON, only delayed leaves are shown = slip>0 (behind schedule) or past due (today > plan end and not done). Delay is a separate axis from state, so it AND-combines with the state filter (e.g., In progress AND delayed). Display-only, axis fixed, summary unchanged, and parent-retention are shared with the state filter. The ON pill is red-tinted (meaning color: delay = red); being a single toggle it has no strike-through.
  • Assignee filter (#93): assignees are variable and many, so instead of pills this is a dropdown (details/summary, a browser standard) + checklist. Assignee values are collected dynamically from wbs.json (unique, empty = "(none)", sorted). Multi-select (OR within the axis) = only checked owners are shown; Select all / Clear all; default = all shown. The badge reads All / a count (N) / the name when only one. It uses an off-set approach (owners you hid are stored in localStorage wbsAsgOff, so new owners are shown by default = robust). It AND-combines with the other axes (e.g., Tanaka AND Done). Display-only, axis fixed, summary unchanged, and parent-retention are shared. The dropdown stays open while you check items.
  • Period filter (#94): a single-select segment of Today / This week / All (default All; remembered in localStorage wbsPeriod). When set, only leaves whose plan or actual period overlaps the target range are shown (this week = Mon–Sun containing today). The axis doesn't move — only rows are filtered (bars don't shift a pixel). AND-combines with the other axes; summary unchanged and parent-retention shared. The selected segment is filled to signal single-select.
  • This filter bar completes the PM's four filter axes (state #91 → delay #92 → assignee #93 → period #94), sharing the common rules OR-within-axis / AND-across-axes / default = no filtering (a full-column Excel-style filter is deliberately not built — to stay lightweight and honest).
  • Column headers are centered. The left info table (No.–Notes) is fixed; only the Gantt scrolls horizontally.
  • Column collapse (outline-style, #64): a thin row above the column headers holds +/− toggles per collapsible unitqty+hours (the breakdown of effort), Effort, Progress, Status, Assignee, Plan, Actual, Notes (No. and Task name are always shown). Collapsed columns are removed at 0 width (no leftover gap stub), the + sits at the boundary (absolute). State is saved in localStorage; scroll/tree-collapse are preserved; collapsing widens the Gantt. Implemented via the COL_CG map + effCols() filter (draw cost = column count, not row-dependent).
  • Plan/Actual date columns have a two-level header: "Plan" / "Actual" on top, "Start / End" beneath (adjacent columns grouped by the group property in COLS).
  • Row layer colors: ◆project (with separators) > L1 > L2 > L3.
  • Gantt: date + weekday (year-month header), weekend + holiday (holidays) columns shaded faint pink full-height (--weekend / a translucent overlay drawn above the rows; bars/inazuma/today-line stay in front for legibility); active tasks extend the actual bar to today. Holidays render red in the date header (Sat = blue / Sun = red convention kept). The holiday name shows as the date cell's tooltip. Plan = unfilled outline (front, 4 sides) / actual = filled bar (behind), overlaid in the same lane (#65): the actual sticking past the outline's right = finish delay = red bar + "+N" (number only; always placed at the bar tip; exact value in the tooltip "Finish delay +N d"), empty space at the outline's left = start delay (actual start is right of the outline's left) — shown by the gap, no dedicated color. Because delays are color-coded (red = finish delay, gray = done), the outline + fill is not misread as a progress bar.
  • Parent (aggregate) = thin summary bar: both plan outline and actual are thin (parent vs leaf by shape, not extra color = CUD-safe, keeps all info when collapsed). The actual's fill ratio matches leaves. Bar color is identical across all levels (parent vs leaf distinguished by bar thickness/shape, not hue or lightness).
  • Colors (CUD-aware, #35): actual = blue / plan = blue outline / finish delay & inazuma = red (vivid while active / muted when done) / done = gray bar. Start delay uses no color — just the empty outline. Following the Okabe-Ito principle we avoid "blue vs purple" (milestone default = mauve #cc79a7) and never rely on color alone (shape, position, labels add redundancy). Verified by tests/e2e/test_color_audit.py (add the pair and re-run whenever you add/change a color).
  • Date columns show 5/11 style. Initial view centers near today.
  • Completed tasks: darker gray row + strikethrough + leading . The gantt actual bar is gray too (blue = active / gray = done at a glance).
  • URLs inside notes are auto-linked (http(s):// only, opens in a new tab). Put plain URLs in note to jump to issues or specs.
  • Overlay (SVG):
    • Inazuma line (red, one line across all projects). Each terminal row's point is placed as follows (bulging left = behind schedule):
      • Completed = on the today line
      • Deadline overrun (started, unfinished, today > plan.end) = at the planned end date (overrun takes priority)
      • Start delay (not started, today > plan.start) = at the planned start date
      • Active (within deadline) = on the today line (start drift is not shown)
      • Everything else (not started, not yet due, etc.) = on the today line
      • A collapsed node contributes a single aggregated point. No explicit today line is drawn (today is the reference).
    • Milestone lines (per-project milestones, arbitrary color; default = Okabe-Ito mauve #cc79a7).

Broken input (graceful degradation)

Policy: broken input must never crash the viewer. Invalid values render as ignored / 0 / empty. Avoid the following when entering data (nothing crashes, but display degrades).

Input (anomaly) Viewer behavior
Invalid date (not "YYYY-MM-DD", or outside 1900–2099) Ignored (plan/actual/milestones/holidays alike). Date cell shows
holidays not an array, or an element with an invalid date Ignored (no red text / no pink column; no crash)
Milestone without label Rendered with an empty label (no crash)
Active but plan.end missing Progress 0% (avoids NaN)
End < start (inverted period) Bar not drawn / looks odd
Actual start in the future Progress 0
qty / hours missing or 0 Effort 0 (shown empty)
Decimal qty (e.g., 0.5) Decimal person-days (1.5 etc.)
Nesting beyond 4 levels Colors stop at L3 (no breakage)
Out-of-range / colorless / invalid-date milestones Not drawn (ignored)
Milestone color not #hex Ignored, default color (prevents attribute injection)
Duplicate ids within one project Collapse keys collide (same ids open/close together)
projects: [] / tasks: [] (empty) Empty view (no crash)
Top level null / number / non-object Empty view (no crash)
Invalid JSON (D&D / file picker / reload) Alert shown (no silent failure)
  • Verification data lives in tests/異常_*.json (broken) and tests/正常_*.json (normal); see tests/INDEX.md.
  • "Never crashes" is verified by loading every test file in headless Chromium and asserting no JS errors and no NaN.

Known limitations

  • Initial rendering slows with thousands of rows (full innerHTML rebuild each render). Mitigation = collapsing + archiving. Virtualization only if it ever truly hurts.
  • Identically-named projects share collapse state (they open/close together). Keep project names unique.
  • null elements inside arrays (null tasks/projects) are unsupported (a non-object top level degrades to an empty view).
  • No keyboard navigation / screen-reader support (mouse-first personal tool).
  • Renaming a project or editing an id in edit mode resets its collapse state (collapse keys derive from name/id).
  • Multi-line note values get flattened to one line when touched in edit mode (inputs cannot hold line breaks).

Notes

  • Chromium-based browsers (Chrome recommended), file:// based (uses the File System Access API).
  • Your own wbs.json is gitignored by default (prevents accidental commits). wbs-archive-*.json is ignored too. Sample = wbs_sample.json; development plan = wbs_roadmap.json.

Dev workflow: the /pm skill (Issue × WBS maintenance)

A skill that keeps GitHub Issues and the WBS roadmap consistent. The Japanese CLAUDE.md holds the full reference (this is the single source; ~/.claude/CLAUDE-single-file-wbs.md symlinks to it). Summary:

  • Split of truth: Issue = problem / challenge / done-criteria; WBS (wbs_roadmap.json) = the work breakdown needed. Linked by #N. The WBS format itself is the "data" sections above.
  • 4 modes (AI picks from context): file (discuss → issue + WBS; optionally an "AI starter memo" — entry files / verify commands / constraints / out-of-scope only, never step-by-step instructions: prompts rot, problems and done-criteria don't) / start (actual.start) / done (auto-verify → close + actual.end) / auto-file on test failure (dedup + threshold).
  • Done is auto-verified (don't close on "should be fixed"): machine-checkable criteria are run (e2e green — command in the private .claude/rules/ as it has a local path; PII grep); visual / save-path smoke is human-confirmed.
  • repo piguo45/single-file-wbs; versioning features=MINOR / fixes=PATCH / breaking=MAJOR (once); a different altitude or artifact is a separate tool (#72).